Word of God Christian Fellowship Church

Word of God Christian Fellowship Church | 12,000 SF FACILITY

8.13.18 - The walls and roof are sheeted. Crewmen are finishing the soffit and installing the trim,

7.20.18 - Roof sheeting is underway,

7.03.18 - Installing additional purlins. Sheeting continues,

6.25.18 - Crewmen have hung all steel and began sheeting the exterior,

6.18.18 - Crewmen have assembled the roof sections and will begin installing once site dries,