5.11.22 - Interior buildout continues, but M&M's work on this project is complete.
3.18.22 - The sheeting is complete. Masonry is underway and crewmen will return to trim the building,
2.15.22 - The building exterior is sheeted and trimmed,
1.19.22 - Crews continue to sheet the roof,
1.04.22 - Crewmen continue to hang steel,