SiteOne Landscape Supply | 12,000 SF Expansion | Friendswood, TX
11.29.23 - Crews are hanging steel for SiteOne Landscape Supply's Friendswood location,
11.29.23 - Crews are hanging steel for SiteOne Landscape Supply's Friendswood location,
10.25.23 - The building is completely sheeted and trimmed,
10.04.23 - Our work is complete on these business suites,
4.20.23 - Our progress installling the insulated wall sheeting,
7.17.23 - We will return to trim the building,
3.01.23 - Crewmen will return to trim the building,
3.08.23 - Crewmen completed their work hanging steel for this project,
2.08.23 - Erectors are hanging steel for the new facility,
3.01.23 - The first two buildings are fully sheeted and trimmed. Sheeting continues for the third unit. There will be 13 buildings total.
10.13.22 - Crewmen are nearing completion installing the metal siding,
7.06.22 - This project is complete,
5.11.22 - Crews are trimming out the wash bay,
5.11.22 - Interior buildout continues, but M&M's work on this project is complete.
1.26.22 - The church facility is complete,
11.10.21 - Crewmen have returned to this project to install the final trim,
9.15.21 - Erectors continue to hang steel,
8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.
9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,
8.24.21 - Erectors are lifting section of roof for Bldg #4,
6.04.21 - Crewmen are relsealing all roof curbs on Hangars 9 & 10
6.03.21 - Crews are resealing roof curbs on Hangar 10
6.02.21 - Crews are reworking the roof curbs on Hangar and repairing leaks on Hangar 8,
11.05.20 - Crewmen are replacing all of the structural bolts and making welding repairs to deteriorated steel rafters,
11.02.20 - Crewmen continue to sheet the roof and install medal siding,
9.18.20 - Crewmen continue to sheet the facility,
9.08.20 - Crewmen have progressed to sheeting the roof,
9.18.20 - Crewmen finished sheeting the mezzanine,
9.08.20 - Progress has been made sheeting the mezzanine. Crewmen are welding the perimeter angle and column washers,
9.18.20 - Crewmen have progressed to installing purlin straps. Sheeting will soon follow,
9.08.20 - Main frame columns are up. Crewmen have progressed to hanging sections of the roof,
7.07.20 - Crews continue to hang steel and have made progress with the metal siding installation,
6.19.20 - The building was delivered.
6.30.20 - This project is complete,
3.30.20 - Crews are wrapping up their work sheeting the building,