Katy Industrial Suites | 26,660 SF Custom Office Condos | Katy, TX
3.22.23 - Crews began hanging steel this week,
3.22.23 - Crews began hanging steel this week,
3.08.23 - Crewmen completed their work hanging steel for this project,
2.08.23 - Erectors are hanging steel for the new facility,
3.01.23 - Crewmen will return to trim the building,
3.01.23 - The first two buildings are fully sheeted and trimmed. Sheeting continues for the third unit. There will be 13 buildings total.
10.13.22 - Crewmen are nearing completion installing the metal siding,
7.06.22 - This project is complete,
5.11.22 - Crews are trimming out the wash bay,
5.11.22 - Interior buildout continues, but M&M's work on this project is complete.
1.26.22 - The church facility is complete,
11.10.21 - Crewmen have returned to this project to install the final trim,
9.15.21 - Erectors continue to hang steel,
8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.
9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,
8.24.21 - Erectors are lifting section of roof for Bldg #4,
6.04.21 - Crewmen are relsealing all roof curbs on Hangars 9 & 10
6.03.21 - Crews are resealing roof curbs on Hangar 10
6.02.21 - Crews are reworking the roof curbs on Hangar and repairing leaks on Hangar 8,
11.05.20 - Crewmen are replacing all of the structural bolts and making welding repairs to deteriorated steel rafters,
11.02.20 - Crewmen continue to sheet the roof and install medal siding,
9.18.20 - Crewmen continue to sheet the facility,
9.08.20 - Crewmen have progressed to sheeting the roof,
9.18.20 - Crewmen finished sheeting the mezzanine,
9.08.20 - Progress has been made sheeting the mezzanine. Crewmen are welding the perimeter angle and column washers,
9.18.20 - Crewmen have progressed to installing purlin straps. Sheeting will soon follow,
9.08.20 - Main frame columns are up. Crewmen have progressed to hanging sections of the roof,
7.07.20 - Crews continue to hang steel and have made progress with the metal siding installation,
6.19.20 - The building was delivered.
6.30.20 - This project is complete,
3.30.20 - Crews are wrapping up their work sheeting the building,
5.28.20 - Crewmen have completed the office siding, installation, and trim,
4.21.20 - The walls and roof are completely sheeted,
3.13.20 - Crewmen are to erect (1) 49'x89' building, (1) 50'x119' building, and (1) 49'x119' building. They will later return to trim the buildings and install the downspouts. Crews are currently erecting the steel,