10.13.22 - Crewmen are nearing completion installing the metal siding,
9.29.22 - Crews continue to side the building,
9.27.22 - Crews have hung most of the steel. Metal sheeting is underway,
9.20.22 - The main frame rafters are up and crewmen are about to lift the roof sections,
9.20.22 - The building materials arrived. Crewmen continue to shake out and erect the steel,