Hoelscher Doors and Weatherstrip | 192,000 SF | Tomball, TX
3.09.20 - M&M's work on this project is complete,
12.30.19 - Macario and his crew are installing trim on the warehouse and finishing the canopies,
12.04.19 - Erectors are one section shy of having the roof fully sheeted,
11.15.19 - Roof sheeting continues and is about 50% complete,
10.29.19 - Crews are assembling and hanging the last of the roof sections. Roof sheeting is also underway,
10.03.19 - Crews are sheeting the roof over part of the warehouse as additional crews hang steel for the office,
9.13.19 - Crewmen are running the purlin straps and welding the inbeds,
9.05.19 - Roof sections are being assembled and lifted,
8.27.19 - Crews are assembling and hanging steel,
8.20.19 - Crews began lifting the tilt wall panels,