11.01.18 - This project is complete,
7.20.18 - Crewmen are nearing completion with their work sheeting the facility,
7.16.18 - Crewmen are finishing the warehouse roof sheeting,
7.06.18 - Crewmen continue to sheet the walls,
7.03.18 - Crewmen have hung all mainframe columns and rafters. Sheeting has begun,
6.25.18 - Crewmen began erecting the building,