Premier | 173,982 SF PEMBs | Baytown, TX
10.26.26 - Our work is complete on this project,
7.28.26 - Erectors are cleaning out the in-beds and preparing to hang steel. Additional crews are cutting out and preparing for the office front windows,
5.16.26 - Crews hung all of the steel for the first building and are installing the metal sheeting,
4.29.26 - Crews are hanging the mane frame columns and purlin rafters,