By KRobinson on Monday, 11 March 2019
Category: Latest News

Texcel

Texcel | 42,000 SF Warehouse Expansion | Houston, TX

3.11.19 - This project is nearing completion,

2.20.19 - Installing gutters and downspouts,

2.05.19 - Sheeting continues,

1.21.19 - Crews are 50% complete with the insulated wall sheeting. The roof sheeting will begin within the next few days, weather permitting,

1.07.19 - Crewmen have erected the main frame columns. Crewmen are assembling and hanging the roof sections,