Ameritex | 30,000 SF PEMB | Conroe, TX
11.02.20 - Crewmen continue to sheet the roof and install medal siding,
9.18.20 - Crewmen continue to sheet the facility,
9.08.20 - Crewmen have progressed to sheeting the roof,
11.02.20 - Crewmen continue to sheet the roof and install medal siding,
9.18.20 - Crewmen continue to sheet the facility,
9.08.20 - Crewmen have progressed to sheeting the roof,
9.18.20 - Crewmen finished sheeting the mezzanine,
9.08.20 - Progress has been made sheeting the mezzanine. Crewmen are welding the perimeter angle and column washers,
9.18.20 - Crewmen have progressed to installing purlin straps. Sheeting will soon follow,
9.08.20 - Main frame columns are up. Crewmen have progressed to hanging sections of the roof,
7.07.20 - Crews continue to hang steel and have made progress with the metal siding installation,
6.19.20 - The building was delivered.
6.30.20 - This project is complete,
3.30.20 - Crews are wrapping up their work sheeting the building,
5.28.20 - Crewmen have completed the office siding, installation, and trim,
4.21.20 - The walls and roof are completely sheeted,
3.13.20 - Crewmen are to erect (1) 49'x89' building, (1) 50'x119' building, and (1) 49'x119' building. They will later return to trim the buildings and install the downspouts. Crews are currently erecting the steel,
3.02.20 - Crews have hung all steel and have sheeted the exterior,
2.12.20 - Crews will began hanging steel for a new Dollar General on 2.17 for Wright Construction.
12.03.19 - Crewmen continue to trim the office,
10.05.19 - Crews are sheeting the office and warehouse,
9.24.19 - Crews erected all main frame columns and are hanging the purlins,
10.10.19 - Final photos of this project,
9.24.19 - Our work on this project is complete,
10.10.19 - This project is complete,
9.24.19 - This project is very near completion,
9.13.19 - Our work on this project is complete,
8.09.19 - Crewmen are finishing the timwork on the building,
9.05.19 - Crews completed their work on the hangar doors and have finished the trim. Their work on this project is complete,
9.03.19 - Crewmen worked on the rolling hangar doors so group 3 could open and close independently of group 6. Crewmen repaired the weatherstrip after separating the sections of rolling door. Crewmen also installed trim between the existing building and the purlins,
3.11.19 - This project is nearing completion,
2.20.19 - Installing gutters and downspouts,
2.05.19 - Sheeting continues,
AIV | 150,000 SF FACILITY
11.06.18 - Crewmen are finishing trim work as this project nears completion,
7.16.18 - Roof sheeting continues.
11.01.18 - This project is complete,
7.20.18 - Crewmen are nearing completion with their work sheeting the facility,
7.16.18 - Crewmen are finishing the warehouse roof sheeting,
11.01.18 - Crewmen are replacing the roof, wall sheeting, and insulation on AMECO's existing 60'x200' steel building,
9.27.19 - Crewmen have completed their work sheeting and trimming this facility,
9.19.19 -
Word of God Christian Fellowship Church | 12,000 SF FACILITY
8.13.18 - The walls and roof are sheeted. Crewmen are finishing the soffit and installing the trim,
7.16.18 - Crewmen have progressed to roof sheeting,
6.25.18 - Samuel Lara is the Foreman for this project of Black Diamond's that began a few weeks ago. Crewmen have erected all steel and have progressed to sheeting the facility,