Premier Cryogenics | 26,000 SF 20-ton Crane-served Manufacturing Facility | LaPorte, TX
10.13.22 - Crewmen are nearing completion installing the metal siding,
10.13.22 - Crewmen are nearing completion installing the metal siding,
7.06.22 - This project is complete,
5.11.22 - Crews are trimming out the wash bay,
5.11.22 - Interior buildout continues, but M&M's work on this project is complete.
1.26.22 - The church facility is complete,
11.10.21 - Crewmen have returned to this project to install the final trim,
9.15.21 - Erectors continue to hang steel,
8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.
9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,
8.24.21 - Erectors are lifting section of roof for Bldg #4,
12.03.19 - Crewmen continue to trim the office,
10.05.19 - Crews are sheeting the office and warehouse,
9.24.19 - Crews erected all main frame columns and are hanging the purlins,
9.13.19 - Our work on this project is complete,
8.09.19 - Crewmen are finishing the timwork on the building,
AIV | 150,000 SF FACILITY
11.06.18 - Crewmen are finishing trim work as this project nears completion,
7.16.18 - Roof sheeting continues.
11.01.18 - This project is complete,
7.20.18 - Crewmen are nearing completion with their work sheeting the facility,
7.16.18 - Crewmen are finishing the warehouse roof sheeting,
Word of God Christian Fellowship Church | 12,000 SF FACILITY
8.13.18 - The walls and roof are sheeted. Crewmen are finishing the soffit and installing the trim,
7.16.18 - Crewmen have progressed to roof sheeting,
6.25.18 - Samuel Lara is the Foreman for this project of Black Diamond's that began a few weeks ago. Crewmen have erected all steel and have progressed to sheeting the facility,
Humble Sign | 20,000 SF Office/Warehouse | Humble, TX
4.25.18 - The building is sheeted and trimwork on the warehouse is complete,
Evalca | 10,000 SF PEMB |Pasadena, TX
3.07.18 - Crewmen have progressed to sheeting and are currently sheeting one of the end walls,
1.04.18 - M&M's work on this project is complete. It is completely trimmed out. Entire project will be complete this week for customer move-in.
7.31.17 - Finishing the roof,