Clover Tool

Clover Tool | PEMB | Waller, TX

2.25.25 - Purlin rafter installation continues. Crews are near completion hanging steel,

 

2.19.25 - Crews began hanging steel for Clover Tool's new facility,

Continue reading
  212 Hits
212 Hits

Scholl Lumber

Scholl Lumber | 32,000 SF PEMB with 42,000 SF canopy | Houston, TX

2.17.25 - This project is trimmed,

10.11.24 - Crewmen have progressed to sheeting the building,

 

Continue reading
  993 Hits
993 Hits

Mchard Independence Business Park

Mchard Independence Business Park | PEMBs | Houston, TX

5.29.24 - These building are complete,

2.22.24 - Finishing the trim,

2.11.24 - This building is complete,

Continue reading
  1530 Hits
1530 Hits

Commons at Timber Creek

Commons at Timber Creek | Two 13,020 SF PEMBs | Friendswood, TX

These Industrial Suites are complete,

 

7.17.23 - We will return to trim the building,

Continue reading
  3759 Hits
3759 Hits

Big City Manufacturing

Big City Manufacturing | 23,000 SF | Friendswood, TX

1.23.24 - Final photos,

 

10.25.23 - The building is completely sheeted and gutters are installed,

Continue reading
  1727 Hits
1727 Hits

SiteOne Landscape Supply Expansion

SiteOne Landscape Supply | 12,000 SF Expansion | Friendswood, TX

1.23.24 - This project is complete,

 

12.14.23 - Crews continue to sheet the building,

Continue reading
  1756 Hits
1756 Hits

Traders Village Houston

Traders Village Houston | PEMB | Houston, TX

1.18.24 - This project is complete,

12.19.23 - Crewmen continue to sheet the building,

Continue reading
  930 Hits
930 Hits

Katy Industrial Suites

Katy Industrial Suites | 26,660 SF Custom Office Condos | Katy, TX

12.14.23 - Final photos,

10.04.23 - Our work is complete on these business suites, 

 

Continue reading
  2372 Hits
2372 Hits

Mid-South Control Line

Mid-South Control Line | Building Addition | Houston, TX

10.26.23 - This project is complete,

9.25.23 - Trimming the exterior,

9.13.23 - Crewmen are installing their pre-assembled roof sections,

Continue reading
  909 Hits
909 Hits

Big Industry Boat and RV Storage

Big Industry Boat and RV Storage | 100,000 SF | Friendswood, TX

These storage units are complete,

 

3.01.23 - The first two buildings are fully sheeted and trimmed. Sheeting continues for the third unit. There will be 13 buildings total.

Continue reading
  2000 Hits
2000 Hits

Humble Sign Co.

Humble Sign Co. | 35,722 SF | Humble, TX

3.08.23 - Crewmen completed their work hanging steel for this project,

 

2.08.23 - Erectors are hanging steel for the new facility,

Continue reading
  1891 Hits
1891 Hits

Premier Cryogenics

Premier Cryogenics | 26,000 SF 20-ton Crane-served Manufacturing Facility | LaPorte, TX

10.13.22 - Crewmen are nearing completion installing the metal siding,

 

 

Continue reading
  2156 Hits
2156 Hits

Elite RV

Elite RV | 70,000 SF Concierge Service Storage Center | Waller, TX

7.06.22 - This project is complete,

5.11.22 - Crews are trimming out the wash bay,

 

Continue reading
  2667 Hits
2667 Hits

20213 Binford Rd

20213 Binford Rd | New 20,000 SF Trade School | Waller, TX

 

5.11.22 - Interior buildout continues, but M&M's work on this project is complete.

 

Continue reading
  2761 Hits
2761 Hits

Connect Church

Connect Church | New 12,000 SF PEMB | Montgomery, TX

1.26.22 - The church facility is complete,

11.10.21 - Crewmen have returned to this project to install the final trim,

 

Continue reading
  2995 Hits
2995 Hits

Inglesia Pentecostal

Inglesia Pentecostal | New 31,116 SF Church Facility 

9.15.21 - Erectors continue to hang steel,

 

8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.

Continue reading
  2741 Hits
2741 Hits

Independence Business Park

Independence Business Park | New 43,000 SF PEMBs | Houston, TX

9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,

 

8.24.21 - Erectors are lifting section of roof for Bldg #4,

Continue reading
  2621 Hits
2621 Hits