Scholl Lumber | 32,000 SF PEMB with 42,000 SF canopy | Houston, TX
10.11.24 - Crewmen have progressed to sheeting the building,
10.03.24 - Crews are hanging steel,
10.11.24 - Crewmen have progressed to sheeting the building,
10.03.24 - Crews are hanging steel,
5.29.24 - These building are complete,
2.22.24 - Finishing the trim,
2.11.24 - This building is complete,
These Industrial Suites are complete,
7.17.23 - We will return to trim the building,
1.23.24 - Final photos,
10.25.23 - The building is completely sheeted and gutters are installed,
1.23.24 - This project is complete,
12.14.23 - Crews continue to sheet the building,
1.18.24 - This project is complete,
12.19.23 - Crewmen continue to sheet the building,
12.14.23 - Final photos,
10.04.23 - Our work is complete on these business suites,
10.26.23 - This project is complete,
9.25.23 - Trimming the exterior,
9.13.23 - Crewmen are installing their pre-assembled roof sections,
These storage units are complete,
3.01.23 - The first two buildings are fully sheeted and trimmed. Sheeting continues for the third unit. There will be 13 buildings total.
3.08.23 - Crewmen completed their work hanging steel for this project,
2.08.23 - Erectors are hanging steel for the new facility,
10.13.22 - Crewmen are nearing completion installing the metal siding,
7.06.22 - This project is complete,
5.11.22 - Crews are trimming out the wash bay,
5.11.22 - Interior buildout continues, but M&M's work on this project is complete.
1.26.22 - The church facility is complete,
11.10.21 - Crewmen have returned to this project to install the final trim,
9.15.21 - Erectors continue to hang steel,
8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.
9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,
8.24.21 - Erectors are lifting section of roof for Bldg #4,
6.04.21 - Crewmen are relsealing all roof curbs on Hangars 9 & 10
6.03.21 - Crews are resealing roof curbs on Hangar 10
6.02.21 - Crews are reworking the roof curbs on Hangar and repairing leaks on Hangar 8,
11.05.20 - Crewmen are replacing all of the structural bolts and making welding repairs to deteriorated steel rafters,
11.02.20 - Crewmen continue to sheet the roof and install medal siding,
9.18.20 - Crewmen continue to sheet the facility,
9.08.20 - Crewmen have progressed to sheeting the roof,