Humble Sign Co. | 35,722 SF | Humble, TX
3.08.23 - Crewmen completed their work hanging steel for this project,
2.08.23 - Erectors are hanging steel for the new facility,
3.08.23 - Crewmen completed their work hanging steel for this project,
2.08.23 - Erectors are hanging steel for the new facility,
10.13.22 - Crewmen are nearing completion installing the metal siding,
7.06.22 - This project is complete,
5.11.22 - Crews are trimming out the wash bay,
5.11.22 - Interior buildout continues, but M&M's work on this project is complete.
1.26.22 - The church facility is complete,
11.10.21 - Crewmen have returned to this project to install the final trim,
9.15.21 - Erectors continue to hang steel,
8.26.21 - Erectors began unloading material Monday and are setting columns and girts today. Brown Construction is the GC.
9.07.21 - M&M crewmen continue to install the wall panels on Bldg #4, and have progressed to installing the end panels,
8.24.21 - Erectors are lifting section of roof for Bldg #4,
6.04.21 - Crewmen are relsealing all roof curbs on Hangars 9 & 10
6.03.21 - Crews are resealing roof curbs on Hangar 10
6.02.21 - Crews are reworking the roof curbs on Hangar and repairing leaks on Hangar 8,
11.05.20 - Crewmen are replacing all of the structural bolts and making welding repairs to deteriorated steel rafters,
11.02.20 - Crewmen continue to sheet the roof and install medal siding,
9.18.20 - Crewmen continue to sheet the facility,
9.08.20 - Crewmen have progressed to sheeting the roof,
9.18.20 - Crewmen finished sheeting the mezzanine,
9.08.20 - Progress has been made sheeting the mezzanine. Crewmen are welding the perimeter angle and column washers,
9.18.20 - Crewmen have progressed to installing purlin straps. Sheeting will soon follow,
9.08.20 - Main frame columns are up. Crewmen have progressed to hanging sections of the roof,
7.07.20 - Crews continue to hang steel and have made progress with the metal siding installation,
6.19.20 - The building was delivered.
6.30.20 - This project is complete,
3.30.20 - Crews are wrapping up their work sheeting the building,
5.28.20 - Crewmen have completed the office siding, installation, and trim,
4.21.20 - The walls and roof are completely sheeted,
3.13.20 - Crewmen are to erect (1) 49'x89' building, (1) 50'x119' building, and (1) 49'x119' building. They will later return to trim the buildings and install the downspouts. Crews are currently erecting the steel,
3.09.20 - M&M's work on this project is complete,
12.30.19 - Macario and his crew are installing trim on the warehouse and finishing the canopies,
3.02.20 - Crews have hung all steel and have sheeted the exterior,
2.12.20 - Crews will began hanging steel for a new Dollar General on 2.17 for Wright Construction.
12.03.19 - Crewmen continue to trim the office,
10.05.19 - Crews are sheeting the office and warehouse,
9.24.19 - Crews erected all main frame columns and are hanging the purlins,